4930 m of steel tube and 3.5 tons blocks of BALPET were installed between 26.01.2008 and 22.02.2008. 18 bar of steel tube was tested and work was completed.
Views of Work
SOİL-SİYAM
Producing 10" steel tube of SİYAM PETROLEUM and installation under sea. Installation of 10" 3860 m steel tube and connecting 10"steel tube of SOIL-SIYAM PETROLEUM between 11.08.2006 and 15.09.2006.
Views of Work
TUBE FLOTATION-INSTALL-UNINSTALL
Installation of 12" steel tube of ALPET CO. Sinking and connecting of 12" steel tube under sea on area of Mersin Soda.
Views of Work
WORK
Collector producing for ALPET CO. Producing and installation of 16” ve 12” collector of ALPET CO. of which buoy system is on area of Kromsan Soda on 12.03.2008.
Views of Work
POAS WORK
Views of Work
SIYAM WORK
Installation of 12" steel tube line on area of Soda.
Views of Work
SOIL WORK
Installation of 12" steel tube line on area of Soda.